Our 10 ways to make your project fundable guide covers what a developer can do to prepare. This one takes the other side of the table: what a development finance underwriter is actually assessing once an application lands on their desk, the specific ratios, documents, and risk factors that determine whether terms are offered, declined, or come back requiring more information. Understanding the criteria itself, not just the preparation checklist, makes it easier to anticipate where a specific project’s application will be tested hardest.
Get your project assessed against real lender criteria.
Sponsor track record and experience
Before a lender looks closely at the numbers, it looks closely at who’s asking for the money. A developer with several completed projects of a similar type and scale in Spain is assessed very differently from a first-time developer, even where the specific deal in front of the lender looks identical on paper. Experience reduces the lender’s perceived execution risk, the chance a project runs over budget, over time, or simply doesn’t get finished to the standard assumed at underwriting. A first-time developer isn’t disqualified, but should expect more scrutiny, a lower loan-to-cost ceiling, and often a requirement for a stronger professional team or a more experienced project manager named on the deal specifically to offset the lack of a completed track record.
Loan-to-cost and loan-to-GDV limits
Metric | What it measures | Typical range |
Loan-to-cost (LTC) | The facility as a percentage of total build cost | 60% to 70% for residential; often lower for commercial or hospitality |
Loan-to-GDV (LTGDV) | The facility as a percentage of projected gross development value | 50% to 65%, whichever of LTC or LTGDV produces the lower figure typically governs |
Day-one loan-to-value | The facility against the site’s current, as-is value at drawdown | Often the binding constraint on a land-heavy or early-stage deal |
A lender will typically size a facility against whichever of these three figures is most conservative, not the most generous. Our GDV calculation guide and good developer margin guide cover how to build a GDV figure a lender will actually accept, stress-tested against a realistic sales or letting scenario rather than the strongest possible outcome, since an underwriter will apply their own, typically more conservative, adjustment to an overly optimistic figure regardless of how it’s presented.
A realistic, third-party-verified cost plan
A lender doesn’t underwrite a developer’s own costing in isolation; it commissions or requires an independent quantity surveyor’s report, and funds are released against that QS’s certification at each stage, not the developer’s internal figures. Our property development costs breakdown is worth building out in the same level of detail a QS would expect to see, since a costing that doesn’t hold together under independent scrutiny is one of the most common reasons an otherwise viable application stalls at valuation stage.
A genuine contingency buffer
Lenders expect to see a contingency line in the costing, typically 5% to 10% of total build cost, and treat its absence as a red flag rather than a sign of confidence. A project costed with no contingency at all reads as either inexperienced or as understating risk, and an underwriter will often simply impose one before proceeding, which changes the funding requirement and can affect the overall loan-to-cost calculation. Building a realistic contingency in from the outset, rather than having one added by the lender later in the process, keeps the numbers the developer controls consistent with the numbers the lender ultimately underwrites against.
Security and legal position
The lender’s security is normally a first-ranking legal charge over the land and the works as they’re built, meaning the loan needs to be able to sit in first position, clear of other charges, easements, or disputes. This is why clean title, confirmed via the nota simple, and clear land classification and planning status, matter as much to the lender as they do to the developer’s own risk. Beyond the property itself, a lender will often also want a personal or corporate guarantee from the developer or its parent company, particularly for a first-time borrower or a thinly capitalised special purpose vehicle, as additional recourse beyond the asset alone.
A credible, evidenced exit strategy
Every facility is assessed on how it gets repaid, and a lender wants evidence for that exit, not just an assumption. For a residential scheme sold to individual buyers, that’s realistic sales absorption rates for the specific location and price point, and increasingly, real pre-sales evidence rather than a projection alone; our apartment development finance guide covers how pre-sales feed directly into this assessment. For a commercial or hospitality asset held as an investment, the exit is typically a refinance into term debt or a sale to an institutional buyer, and a lender will want to see the letting or trading assumptions behind that exit stress-tested against a less favourable market, not just today’s pricing; our commercial property development finance guide covers this in more depth for income-producing assets specifically.
The professional team named on the deal
Beyond the QS providing cost certification, a lender wants to see an architect and, on larger schemes, a project manager already engaged and named, with relevant experience for the specific asset type and scale. A team with a track record on comparable projects reduces perceived execution risk in the same way developer experience does, and a lender will often ask directly about the team’s prior projects as part of underwriting, not merely note that a team exists on paper.
Company structure and financial standing
A lender wants to see a properly incorporated Spanish entity, generally an SL, with clean, complete company and tax documentation, and increasingly wants visibility on the developer’s own broader financial standing beyond the single project, existing liabilities, other live developments, and general balance sheet strength. Our how to set up a property development company guide covers getting this foundation right, and a structure still being assembled at application stage is a common, avoidable source of delay once underwriting has otherwise progressed.
How this differs between bank and private lenders
A mainstream bank applies these criteria in a fairly standardised, often more rigid way, generally offering the lowest cost of capital to a project that clears every threshold comfortably. A private lender typically applies the same underlying criteria but with more flexibility on any single factor, a first-time developer with a strong team, or a slightly thinner contingency offset by other strengths in the deal, in exchange for a higher cost of capital. Our private lending vs. bank finance comparison and private capital guide cover this trade-off in more depth, and knowing which criteria a specific project is weakest against is genuinely useful in deciding which type of lender to approach first.
Where this fits into the wider process
Our 10 ways to make your project fundable guide turns this underwriting picture into a practical preparation checklist, and our development finance timescale guide covers how the strength of an application against these criteria directly affects how long the process takes. For anyone earlier in the process still weighing whether to develop at all, our how to become a property developer in Spain guide is a useful starting point.
Find out how your project measures up before you apply.
FAQs: what Spanish development lenders assess
What loan-to-cost can I typically get for a development project in Spain?
Commonly 60% to 70% for residential schemes, often lower for commercial or hospitality projects, with the facility ultimately sized against whichever of loan-to-cost or loan-to-GDV is more conservative.
Do lenders require a contingency buffer in the cost plan?
Yes, typically 5% to 10% of total build cost. Its absence is generally treated as a red flag, and a lender will often impose one before proceeding if it isn’t already built in.
Does a first-time developer get worse terms than an experienced one?
Often, yes, since a lender perceives more execution risk without a completed track record. This can mean a lower loan-to-cost ceiling or a requirement for a stronger, more experienced professional team on the deal.
Do I need pre-sales to satisfy a lender's exit strategy requirement?
Not always, but real pre-sales evidence materially strengthens a residential scheme’s exit assessment compared to a sales projection alone, particularly for a first-time developer or a less established location.
What security does a Spanish development lender typically take?
Normally a first-ranking legal charge over the land and works as built, clear of other charges or disputes, often alongside a personal or corporate guarantee, particularly for a first-time borrower or a thinly capitalised company.
Are private lenders more flexible than banks on these criteria?
Generally, yes. A private lender typically applies similar underlying criteria but with more flexibility on individual factors, in exchange for a higher cost of capital than a mainstream bank.
This article is for informational purposes only and does not constitute financial, tax, or legal advice. Spanish property, tax, and lending rules change regularly and depend on your specific circumstances. Always consult an authorised mortgage broker, a qualified Spanish tax advisor, and an independent legal professional before entering into property or financing agreements.